PROJECT PORTFOLIO
Kilcoo Wastewater Treatment Works

Kilcoo Sludge Tank Installation

Kilcoo HMI
| Client: | DRD Water Service (NI) |
|---|---|
| Main Contractor: | W.I.S. Ltd. |
| Contract Value: | £1.1m |
| Contract Period: | 10 mths |
This project involved the construction of a new Wastewater Treatment Plant on the existing site, consisting of 2 no. RBCs, 2 Primary and 2 Final Settlement Tanks, 1 no. Huber R09 Inlet Screen, 30 day sludge holding capabilities and various pumping stations controlled via the HMI on the WIS manufactured Motor Control Centre.
The plant has been designed to deal with the anticipated population of 900 people and the effluent quality will be less than:
BOD: 40mg/l
Suspended Solids: 60mg/l
Ammonia: 15mg/l